Page 9 - 2022 - Q1 - Minerva in Focus
P. 9

“                                                                                                               SAFETY & SECURITY


        On arriving at the LGSP
        cabinet, the cadet found the
        unconscious and unresponsive                                                        Figure 3:
        electrician lying on the deck                                                       IG scrubber pump
                                                                                            starter contacts and
        with his head and hands                                                             the missing star
                                                                                            contactor spring
        inside the lower section.                                                           Source: Investigation
                                  ”                                                         report by Republic of

                                                                                            the Marshall Islands
                                                                                            Maritime Administrator

        The door for the IG scrubber pump starter panel was fully open,   The ship diverted to a nearby port, where the electrician was trans-
        and the lower panel covering the 440V power terminals had been   ported ashore the same day and pronounced dead. The cause of
        removed and placed to the left of the cabinet (Figure 1).  death was consistent with electrocution.

        The cadet alerted the third engineer (3/E) and motorman working   The main circuit breaker supplying power to the pump starter
        nearby. They then moved the electrician further away from the   (inside the IG scrubber pump starter panel) was found in the off
        open LGSP cabinet, found he had no pulse, and started cardiopul-  (open) position. The star contactor for the pump starter was miss-
        monary resuscitation (CPR).                         ing a spring and cover locking pin (Figure 3). These were found on
                                                            the cabinet’s lower framing and deck. The investigation presumed
        The master was subsequently advised, a general alarm was raised,   that the electrician inadvertently touched the energized 440V pow-
        and emergency medical equipment was brought to the scene.   er terminals in the cabinet’s lower section while retrieving the star
        Despite continued CPR, the electrician could not be resuscitated.     contactor spring or the cover locking pin.

           Lessons Learned                                     member to be present, which could have resulted in an ap-

                                                               propriate challenge and stopped the unsafe work.
                                                            •   The Company’s Stop Work Authority (SWA) policy required
           The following lessons learned have been identified based on   that all crew members take action to prevent observed
           the  information available in the investigation  report and are   unsafe acts or conditions. Using this authority, the 2/E and
           not intended to apportion blame on the individuals or company   engine cadet could have prevented the electrician from un-
           involved:                                           dertaking the task.
                                                            •   An effective and timely scheduled maintenance would have
           •   A formal risk assessment, as required by the SMS, should   resulted in recording and rectifying the missing physical
               have identified the hazards of working in the cabinet with   safety barriers within the LGSP cabinet and prevented the
               440V power cables and terminals, and would have resulted   electrician from accidental contact with energized circuits.
               in adequate risk mitigation.                 •   Although it did not contribute to the incident, the cadet
           •   Completing a PTW, as required by the SMS, would have result-  could also have been electrocuted when he immediately
               ed in the LOTO procedures being applied and ensured that   pulled the electrician from the LGSP cabinet, as he had not
               the circuits and equipment in the work area were de-ener-  ensured that the power was isolated or that the electrician’s
               gized. They would have also prevented the electrician from   body was not energized.
               accessing the cabinet while the 440V power input was not
               secured.
           •   A work-specific Toolbox Talk could have helped with appro-  The source of this case study is an investigation conducted by the Re-
               priate pre-task hazard identification. The engineering officers   public of the Marshall Islands Maritime Administrator.
               were reportedly unaware that the electrician was completing
               this work, and a Toolbox Talk had not been held with him.   The purpose of this case study is to support and encourage reflective
           •   The Company’s SMS required that all scheduled work be   learning. The details of the case study may be based on, but not neces-
               planned at least one day in advance to allow time for com-  sarily identical to, facts relating to an actual incident. Any lessons learned
               pleting the required safety procedures. During the morning   or comments are not intended to apportion blame on the individuals
               planning meeting, the electrician was not questioned or   or company involved. Any suggested practices may not necessarily be
               prevented from undertaking the unplanned work.  the only way of addressing the lessons learned and should always be
           •   The electrician was working alone when the incident oc-  subject to the requirements of any applicable international or national
               curred. A completed PTW would have required another crew   regulations, as well as a company’s own procedures and policies.



                                                                                                           9 9
   4   5   6   7   8   9   10   11   12   13   14