Page 11 - 2021 - Q3 - Minerva in Focus
P. 11

“


        As he did not observe any
        leakage, the 3rd Engineer

        pulled the cover without
        removing the nuts. However,
        hot oil started splashing                                                           Figure 3:
        onto him from the manhole                                                           The manhole at the

        bottom while he was still on                                                        aft side of the tank,
        the folding ladder.                                                                 almost one meter from
                                                                                            the bulkhead and two
                                  ”                                                         Source: HBMCI
                                                                                            meters from the floor.


        Engineer away and took off his coverall, which was soaked with   first aid to the 3rd Engineer. A helicopter arrived about two hours
        the hot oil. The engine crew then moved the 3rd Engineer to the   after the accident. The 3rd Engineer’s condition was considered
        vessel’s hospital, where it was observed that he had sustained   relatively good when he left the vessel as he managed to walk by
        serious burns to various areas of his body. In the meantime, the   himself to board the helicopter. The 3rd Engineer was transferred
        Master was informed about the incident.             to a Sao Luis hospital, where he was diagnosed with second-degree
        The Master reported the incident to the company, then contacted   burns on a large part of his body. He was admitted to the Intensive
        the local agent and requested the immediate transfer of the 3rd En-  Care Unit and remained hospitalised for the next 12 days until he
        gineer ashore for treatment. Meanwhile, the Chief Officer provided   died of septic shock.



           Lessons Learned                                  •    Taking  shortcuts  from  an  established  safe  work

                                                                 procedure to save time and effort may be appealing
                                                                 but can lead to undesirable and even tragic conse-
           The following lessons learned, which are not intended to   quences. Other ways of confirming the tank had
           apportion blame on the individuals or company involved,   been drained could have been used - for example, by
           have been identified based on the available information in   measuring the quantity in the BSO Tank; this would
           the investigation report:                             have helped identify that it was not safe to open the
                                                                 manhole cover.
           •    The  investigation  found  that  the  potential  hazards   •   The vessel’s Planned Maintenance System (PMS) did
                associated with the unknown amount of hot sludge in   not address the foreseeable and preventable jam-
                the tank due to the malfunctioning level gauge had not   ming of the level gauges with sludge oil. It did not
                been identified. A simple, complete, and meaningful risk   provide guidelines for periodic routine maintenance/
                assessment needs to be conducted before starting a task   tank cleaning. Providing an appropriate and regular
                to identify the hazards and required precautions; this will   regime for cleaning the tank would have helped avoid
                also help personnel maintain focus when most needed.   the need for this unplanned and hazardous task.
           •    Making assumptions about the safety of the work   •   The WOS Tank was not fitted with a sounding pipe as
                environment can lead to unexpected exposure to haz-  an alternative means when the level gauge malfunc-
                ards and injury. Experience and professional knowl-  tioned. Although not a requirement, had a sounding
                edge may not be enough to address the safety gaps   pipe been fitted, this would have allowed the two
                resulting from a risk assessment based on incomplete   engineers to verify the tank’s contents.
                hazard identification.                      •    The 3E was wearing a common cotton coverall provid-
           •    Confirmation bias (favouring information that con-  ed to him by the company. This only offered limited
                firms one’s pre-existing beliefs) can create a window   protection from heat and allowed the hot liquid to
                of opportunity for an incident. This can be avoided by   penetrate and transfer heat to the skin. The investi-
                personally challenging oneself to take a minute and   gation identified that an ISO 11612 compliant coverall
                think about the job at hand – to consider what can   could have possibly provided better protection to the
                go wrong and how and what steps one can personally   3E despite being intended to protect against heat and
                take to minimize the risk.                       flame rather than hot liquids.



                                                                                                           9
   6   7   8   9   10   11   12   13   14   15   16