Page 23 - 2022 - Q4 - Minerva in Focus
P. 23

Attending the gas trials of Minerva Amorgos





        Mrs  Foteini  Volaki  had  attended  the  Gas   The gassing up and cooling down of the   ambient temperature to prevent the forma-
        Trials of Minerva Gas' newly built Minerva   remaining three tanks was conducted after   tion of dry ice by the CO2 contained in the
        Amorgos at SHI in South Korea and pre-  unberthing the LNG Terminal for three days   inert gas and condensation of the water. Cold
        sents her experiences.             in total. During the cooling down of one cargo   Natural Gas was taken from all tanks and
                                           tank, a certain amount of BOG is generated.   returned to their bottom in Warm Natural
        As per SIGTTO, the term ‘Gas Trials’ encompass-  This BOG was used to gas up the next cargo   Gas form, at approximately +80oC, produced
        es those tests undertaken when a quantity of   tank before its cooling down. This sequential   by HD compressors and warm-up heaters.
        LNG is taken onboard for testing shipboard   operation resulted in no natural gas being   In that way, the introduced hot gas caused
        machinery at the design temperature. Gas   vented into the atmosphere since all gas was   the evaporation of the unpumpable LNG. The
        Trials are carried out prior to the vessel en-  consumed gradually by the consumers and   warm-up operation was continued until the
        tering service to confirm the correct function,   oxidized by the GCU.  secondary barrier’s temperature indicated at
        integrity, and capacity of the complete cargo   During the Gas Trials, the Gas Management   least +5 °C.
        system, including containment, insulation, car-  System (GMS) of the main propulsion engines,   Then, the tank inerting was carried out. In
        go handling equipment, pipelines, valves, and   the diesel generator engines, and the gas   this process, warm natural gas exits from the
        the equipment handling the boil-off-gas.   combustion unit, including cargo handling   top of each tank and is displaced by nitrogen
        The procedure adhered to for Minerva Amorgos   equipment, such as low-duty compressors   introduced at the bottom through the liquid
        diverged  from  the  methods  followed  for  her   and forcing vaporizers, was also confirmed.   filling line as heavier gas. The procedure’s
        two sister vessels (Minerva Kalymnos & Min-  After completing the Self Checks, Safety Tests   purpose is to avoid having an air/NG mixture
        erva Chios), with the main difference being the   were carried out, including the Gas and Pilot   within the flammable range. Hence the tar-
        gassing up, cooling down, and loading of only   Trip Tests, and changeovers were conducted on   get is a hydrocarbon content of cargo tank
        one tank alongside the Terminal.   both M/Es and DGs. Subsequently, the cargo   ≤ 2% in volume. All associated cargo piping
        The Gas Trials began with the tanks and barri-  tank pressure control was achieved using the   and equipment are filled with N2 by flow
        ers already inerted with GN2 to prevent a flam-  BOG as fuel on MEs and DGs and with GCU and   establishment during this operation.
        mable atmosphere, followed by the gassing-up   sub-cooler use.       Tank aeration was the last step, concluding
        process after berthing at the Terminal, where   During the cargo pump tests, each cargo tank   the vessel’s Gas Trials scheme. Dry air was
        the GN2 at Tank No.4 was displaced by intro-  was stripped of cargo to the minimum level,   introduced at the top of the tanks through
        ducing warm natural gas. Basically, at this stage,   and LNG was gathered again in the No.4   the vapor line, and nitrogen was discharged
        LNG is supplied by the Terminal to the vessel’s   cargo tank. The vessel returned to the Ter-  from the bottom through the filling line and
        LNG vaporiser through the spray line. The pro-  minal, and the remaining LNG was unloaded,   the liquid header to the No.1 vent mast. Once
        duced warm natural gas enters the tank via the   reaching the unpumpable level as far as   the O2 content is raised to 20% in volume,
        vapor line, while the GN2, as a heavier gas, is   practicable. Before cargo tank inerting and   entering cargo tanks is permitted for inspec-
        vented through vent mast No.1. On completion   aeration, the cargo tank was warmed up to   tions, cleaning, or repairs.
        of gassing up the No.4 cargo tank, it is then
        cooled down before loading to a temperature
        of -130oC. The purpose of cooling down is to
        lower the temperature of the tank walls, pump
        tower, and insulation at a controlled rate, there-
        by reducing thermal stresses and the volume of
        boil-off gas generated during the early stages
        of loading. Approximately 4,400 m3 of cargo
        was loaded at Tank No.4, and the generated
        BOG was returned with free flow to shore.















        by Foteini Volaki
        Terminal Compatibility Officer     Photo 1: GCU Safety Test           Photo 2: Interior of Mark III Flex + after aeration
        Minerva Gas Inc.


                                                                                                          23 23
   18   19   20   21   22   23   24   25   26   27   28